Installation
How does measuring and installing a worktop work?
Last updated:
For worktops in the Netherlands and Belgium, measuring and installation are always included. Here's how it works:
- You order your fronts and worktop. We send the sketch to the factory.
- About 7 weeks after you place your order, our worktop partner calls you to schedule the measuring visit. This takes place about a week after your fronts are delivered.
- You or your installer first install the basic kitchen: cabinets, fronts, panels, plinths and handles. The cabinets must be secured and level.
- During the measuring visit, the exact dimensions are recorded. If the lengths differ, you'll receive an additional invoice.
- The worktop is installed 2 to 4 weeks after the measuring visit. A sink is fitted at the same time, but a tap and hob are not. Sealing the worktop with silicone is not included as standard.
- You arrange for a plumber and electrician to connect the water and electricity.
In the meantime, you can temporarily use your own worktop. A worktop can have an unsupported overhang of up to 25 cm. If it's more, for example for a breakfast bar, support brackets are needed (€ 299). If the measuring visit shows they aren't needed, we'll refund this amount.